** Workplaces are still not safe for women ** 10 killed in apartment fire in northwest China's Xinjiang ** Richarlison's second-half brace give Brazil 2-0 win over Serbia ** Son, Suarez subdued in Uruguay-Korea stalemate ** Raising retail power tariff: 3 more distribution companies submit proposals ** 6 hurt in three-wheeler crash on Mayor Hanif Flyover ** FIFA World Cup 2022: Young Spain rout experienced Costa Rica 7-0 ** Japan stun Germany with late strikes at World Cup ** Hundreds of vehicles get clogged with heavy traffic congestion in city’s Tejgaon area on Saturday. NN photo ** Japan stun Germany 2 goals in 8 minutes ** Bangladesh arrests man tied to death-row militants’ escape ** Traffic alert: Dhaka commuters urged to avoid Airport-Uttara route from tomorrow till Sunday morning ** A man dries up fishes at Bakolia area of Chattagram city on Tuesday ahead of imminent winter. NN photo ** Clothing piles up at Bangladesh warehouses as west cuts imports ** Six cops among 21 injured as police clash with BNP in Sherpur ** FIFA World Cup 2022: Saudi Arabia beat Argentina 2-1 ** Fire kills 38 at industrial wholesaler in central China ** Bangladeshi fisherman injured in firing by Myanmar border force ** Our police are not serious about their professionalism and honesty ** Saka, Bellingham sparkle as England crush Iran ** Death toll in Indonesia quake rises to 162 ** Earthquake shakes Indonesia’s Java island; at least 20 dead ** Bulk power price hiked by around 19.92 % ** Transport strike in Habiganj rolls into 4th day ** Valencia leads Ecuador to 2-0 win over hosts Qatar in World Cup opener **

Bridge cranes installed at Unit 2 of Rooppur NPP

29 September 2022
Bridge cranes installed at Unit 2 of Rooppur NPP


UNB, Dhaka :

Two bridge cranes have been installed in the turbine compartment of Unit-2 of Rooppur Nuclear Power Project.

According to Rosatom, the Russian contractor of the project, the cranes will be used for construction and installation works, and for NPP reconstruction, repair, and upgrade during operations.

A branch of Rosatom Engineering Division- VdMU did the installation of cranes having a lifting capacity of 50 and 180 tons.

Weights of the cranes with additional equipment were about 130 and 210 tons respectively. The heaviest and largest components were installed in the design position using the Liebherr 11350 crane with a lifting capacity of 1350 tons.

“Installation of bridge cranes is a complex technological process involving more than a hundred operations”, said Alexey Deriy, ASE Vice President and Director for Rooppur NPP construction project.

“Its successful completion allows proceeding to the next construction stage, which is the installation of the turbine compartment equipment, in particular, the main and auxiliary equipment of the turbine set”, he added.

Rooppur NPP will be equipped with two Russian 3+ generation VVER-1200 reactors of a total of 2,400 MW.

This type of reactor meets all the international safety requirements. The engineering division of Russia’s Rosatom State Corporation is the designer and general contractor of the project.

According to Bangladesh Atomic Energy Commission, the implementing authority of the RNPP, the first unit of the power plant was scheduled to start operation in 2022 and second one in 2024.

But recently the first unit's operation was rescheduled to 2024 and second unit to 2025.